Project Information
Wharfdale Park
-
- Location
- Tyseley, Birmingham
-
- Value
- £11,100,000
-
- Duration
- 60 Weeks
-
- Completed
- March 2018
-
- Breeam Rating
- Very Good
Project Overview
Design and Construction of Four Industrial Units totalling 201,000 sqft (Unit 1 - 15,000 sqft, Unit 2 - 44,000f sqft, Unit 3 - 120,000 sqft and Unit 4 - 22,000 sqft).
Vibro Stone Column Ground Improvement Foundation and Floor Slab Solution.
Integral Ground and First Floor Offices totalling 18,000 sqft (Unit 1 - 2,200 sqft, Unit 2 - 4,400 sqft, Unit 3 - 9,000 sqft and Unit 4 - 2,400 sqft).
Phased construction to allow the occupation of Unit 1 prior to the commencement of Unit 4.
12 Dock Levellers (Unit 2 - 2 and Unit 3 - 10).
9 Level Access Doors (Unit 1 - 2, Unit 2 - 2, Unit 3 - 2 and Unit 4 - 3).
External Works comprising Section 278 Works, Access Road, Service Yards and Car Parks.