Steel & Alloy Processing

Steel & Alloy Processing

Project Information

Steel & Alloy Processing


    • Location
    • Oldbury, West Midlands
    • Value
    • £11,300,000
    • Duration
    • 38 Weeks
    • Completed
    • February 2018
Project Overview

Design and Construction of an Industrial Unit totalling 120,000 sqft (Manufacturing & Distribution Unit - 115,000 sqft and Scrap / Utility Unit - 5,000 sqft).
Precast Concrete Piled Foundation and Floor Slab Solution.
Integral Ground Floor Offices totalling 1,700 sqft.
Manufacturing & Distribution Unit comprising of Four Halls with Three Overhead Cranes.
A Slitting Line with 12 metres Deep Pit and Blanking Line with 40 metre Underground Tunnel linked to the Scrap / Utility Unit.
6 Level Access Doors.
External Works comprising Service Yard and Car Park.