Project Information
Steel & Alloy Processing
-
- Location
- Oldbury, West Midlands
-
- Value
- £11,300,000
-
- Duration
- 38 Weeks
-
- Completed
- February 2018
Project Overview
Design and Construction of an Industrial Unit totalling 120,000 sqft (Manufacturing & Distribution Unit - 115,000 sqft and Scrap / Utility Unit - 5,000 sqft).
Precast Concrete Piled Foundation and Floor Slab Solution.
Integral Ground Floor Offices totalling 1,700 sqft.
Manufacturing & Distribution Unit comprising of Four Halls with Three Overhead Cranes.
A Slitting Line with 12 metres Deep Pit and Blanking Line with 40 metre Underground Tunnel linked to the Scrap / Utility Unit.
6 Level Access Doors.
External Works comprising Service Yard and Car Park.