Phase 1, Symmetry Park

Phase 1, Symmetry Park

Project Information

Phase 1, Symmetry Park


    • Location
    • Aston Clinton, Aylesbury
    • Value
    • £11,800,000
    • Duration
    • 36 Weeks
    • Completed
    • November 2019
    • Breeam Rating
    • Very Good
Project Overview

Design and Construction of Three Industrial Units totalling 248,000 sqft (Unit 1 - 83,000 sqft, Unit 2 - 55,000 sqft and Unit 3 - 110,000 sqft).
Project undertaken following the administration of Calcroft at the point of two steel frames erected.
Integral First and Second Floor Offices totalling 23,000 sqft (Unit 1 - 8,000 sqft, Unit 2 - 5,000 sqft and Unit 3 - 10,000 sqft).
21 Dock Levellers (Unit 1 - 7, Unit 2 - 4 and Unit 3 - 10).
11 Level Access Doors (Unit 1 - 4, Unit 2 - 3 and Unit 3 - 4).
External Works comprising Access Road, Service Yards and Car Parks