Project Information
Pantheon Park
-
- Location
- Wednesfield, West Midlands
-
- Value
- £11,100,000
-
- Duration
- 44 Weeks
-
- Completed
- February 2020
-
- Breeam Rating
- Very Good
Project Overview
Design and Construction of Three Industrial Units totalling 248,000 sqft (Unit 1 - 30,000 sqft, Unit 2 - 83,000 sqft and Unit 3 - 135,000 sqft).
Drilling & Grouting and Asbestos & Japanese Knotwed relocation. Ground Bearing Foundation and Floor Slab Solution.
Integral First Floor Offices totalling 13,000 sqft (Unit 1 - 3,000 sqft, Unit 2 - 4,000 sqft and Unit 3 - 6,000 sqft).
20 Dock Levellers (Unit 2 - 8 and Unit 3 - 12).
9 Level Access Doors (Unit 1 - 3, Unit 2 - 2 and Unit 3 - 4).
External Works comprising Access Road, Service Yards and Car Parks.